by Glenn C. Koenig, Webmaster at Town Wide Mall
Because of the situation, the bridge was temporarily closed in both directions. Personnel on site this evening told me that the hole, although significant in size, did not appear to extend all the way through the bridge deck. If the inspection underway shows that the bridge will be safe once the hole is filled in, later during the night, the work should be completed by morning. However, if more serious damage is found, the bridge may have to be closed for a longer time.
Alternatively, drivers could to turn left, head up Walnut Street, then turn right on Thompson Street, and work their way back around to Main Street on the other side of the Mill Pond.
The photo below was taken from the Assabet River Rail Trail pedestrian bridge just a few yards up river from the Memorial Bridge. You can see the river as it passes directly under the bridge, at the center of the image. (Story continues, below) The photo below, shows the work getting underway. I took it from the opposite direction, with the Post Office behind me and Mill & Main to the right. According to Maynard Public Works Director, Justin DeMarco, the Massachusetts Department of Transportation (Mass DOT) has sole responsibility for the maintenance, repair, or replacement of this bridge. Therefore, our local Public Works department was not involved in the repair and local taxes are not impacted. DeMarco stated that Mass DOT has implied that the bridge will be replaced some time in the near future, but at this point, "... we have no confirmation of when, and what the impacts or implications will be for the Town of Maynard." Commentary
Construction to replace the Florida Road bridge began in early 2022 and was completed by the end of 2023, just under two years. However, there is much more to the story because of how long it took before that to "get in line" on the state's roster of bridge replacements, work up the design, apply for the necessary permits, and finally secure the funding to go ahead. The world is a very different place from what it was in 1922, when the Memorial Bridge was constructed. In general, towns can no longer afford to fund the replacement of bridges such as this one, so the state has assumed responsibility for all aspects of the cost, scheduling, design, and construction. The challenges facing the replacement of the Memorial Bridge are greater than they were for the Florida Road bridge because of the amount of traffic it handles and it's critical location for Maynard's traffic flow. Florida Road was more of a "shortcut" for drivers, heading up to Summer Street. The detour was inconvenient, but we managed. However, Main Street carries Route 62 traffic between Concord and Acton, to the East, and on to Stow, and Route 495, to the west. But that's not all. As the state has grown in population over the last century or so, more and more bridges were built that now need replacing. This story explains some of the challenges we face in getting this work done: https://mass.streetsblog.org/2022/08/31/its-not-just-the-t-analysis-finds-unusually-large-backlog-in-commonwealths-bridge-repair-needs In the mean time, we're stuck paying for necessary repairs (from state funds) until a replacement can be scheduled. Town Wide Mall is free for anyone to read and carries no advertising, so our only means of support is from donations. Please consider helping with a donation of any amount. Click on the Donate button, below, to see the options.
2 Comments
David Mark
9/7/2024 09:22:26 am
A mention that the Walnut Street bridge and the Route 117 bridge also date to 1922, are of similar construction (rebar reinforced concrete) and are likewise overdue for replacement, although not as physically compromised as the Main Street bridge.
Reply
Dinesh
9/12/2024 01:19:36 pm
I have been keeping an eye on this to see if there will be any movement ever.
Reply
Leave a Reply. |
AuthorWrite something about yourself. No need to be fancy, just an overview. Archives
September 2024
Categories |